Current Projects

 2016 Water/Wastewater Renovation & Replacement Project - Phase 1
 
Deborah Avenue, David Avenue, Basin “B” Outfall Lines
• Engineer: Dick Perkins, P.E.
Contractor: No Dig Tech.
Project: The 2016 R & R Project includes various locations with varying degrees of deterioration of the existing clay tile sewer lines and cast iron water lines. In most cases the infrastructure is 40-50 years old. The water and sewer main lines will be replaced with
Polyvinyl Chloride (PVC) pipe. In addition, water service lines will be replaced (City side of the meters) and sewer lines will be replaced up to the property lines with cleanouts being installed at the property line. 

Project Status: 
Construction started (10/17)
                             Construction is 35% complete (11/17)
                             Construction is 55% complete (12/17)                                                                                                                     
                 
                             Construction is 99% complete (1/18)
                             Construction is 99% complete (2/18)
                             Construction is 99% complete waiting on sod placement (3/18)
Projected Completion Summer 2018

2016 Water/Wastewater Renovation & Replacement Project - Phase 2
 
Various Locations
• Engineer: Dick Perkins, P.E.
Contractor: TBD
Project: The 2016 R & R Project includes various locations with varying degrees of deterioration of the existing clay tile sewer lines and cast iron water lines. In most cases the infrastructure is 40-50 years old. Project location is from, N. Westmoreland Rd. Water Line (St.
Anne Episcopal Church North to Cedar Rapids Ln. ). Phase II will consist of Street Reconstruction of both Deborah and David Avenues. 
Project Status: 
Phase II contract will be advertised for bids starting on October 8, 2017 (9/17)
                             Phase II has been bid (10/17)
                             Phase II has bid and will be presented to City Council for award on December 19 2017 (11/17)
                             Presentation to City Council for award delayed until January 16, 2018 (12/17)
                             Project awarded by City Council on January 16, 2018 (1/18)
                             Awaiting Pre-Construction Meeting (2/18)
                             Project slated to start on April 16, 2018 (3/18)
Projected Completion Summer 2018